Maersk Oil celebrates latest milestone on way to Culzean first gas

Jul 24, 2017

Maersk Oil said today that it had reached another key milestone ahead of first gas from its flagship North Sea Culzean field.

The installation of jackets for the central processing facility and the utilities and living quarters were completed yesterday.

The wellhead platform’s jacket was fitted at the site last year.

All three structures were built by Heerema an installed using Heerema Marine’s Thialf crane vessel.

Culzean lies about 145 miles east of Aberdeen and is expected to produce between 60,000 and 90,000 barrels of oil equivalent at plateau for at least 13 years.


Full Article:  https://www.energyvoice.com/oi...